Introduction
This technical document provides additional guidance relating to how developments in coastal locations can meet the requirements of our technical manual.
For the purposes of Warranty, coastal locations are:
The 'key risks' to construction in Coastal locations are: Wind Speed, Rain Penetration, Durability of Materials, Workmanship and Maintenance.
Developments in coastal regions, particularly in the South West, West and North West areas of the UK are at a much greater risk of exposure to aggressive environment than inland areas. The most vulnerable areas being within 500m of the shoreline, but the aggressive environment can also have an effect on buildings as far inland as 5km.
Key Risks
Gust wind speeds, in combination with rain, can create design issues for buildings sited in shoreline locations, particularly cladding and roof coverings and their associated fixtures and fittings. The slightly less obvious risks of durability, workmanship and maintenance, equally impact on the longevity of a building. For example, the effects of corrosion from windblown salt spray and higher UV exposure will reduce the expected durability of a finish or a component in a coastal location to less than 10 years, in some cases as short as 5 years.
Failures directly due to poor workmanship rather than the failure of the actual material are common. For example:
Whilst it’s the designer’s responsibility to ensure that exposed components must be fit for purpose; some materials and particularly finishes will, due to the environment, require an on- going maintenance to keep a satisfactory finish. Maintenance plans will need to be drawn up by the designer to ensure premature failure of coatings or components is avoided. The building owner must then take responsibility to ensure that regular maintenance of exposed components and finishes is carried out. For example:
Masonry wall constructions
In severe and very severe categories of exposure, external walls should incorporate additional protective features to avoid excessive wetting of the masonry. Features such as deep overhanging eaves and verges, projecting sills and checked window reveals should be incorporated into the design.
The following should be avoided in very severe exposures:
Rendering
The 'background' or substrate which supports the render must be suitable for bonding the render to and be sound and dry in condition. Hand mixed renders should not be used. Only pre-blended bagged render systems will be accepted that have a third party accreditation such as a BBA or ETA certification and backed up with a manufacturer’s specification. In a very severe location, a detailed specification from the render manufacturer will be required to justify it is suitable for the proposed conditions and the overall thickness.
Render angle beads should be appropriate for the environment. Non-corrosive render beading e.g. PVC or marine grade stainless steel should be installed.
External Cladding systems including rain screens
The materials used within the construction should be capable of withstanding weathering and atmospheric pollution and potential chemical attack for the intended design life. The system must have a current third party product approval, confirming the specification is suitable for a coastal environment.
Window and doors
The choice of windows and doors must be supported by manufacturer’s certification to confirm they meet the design weather conditions and have proof of testing to the following weather performance standards:
Window and door furniture and fittings must be resistant to the effects of the saline environment.
Balconies and terraces forming a roof
The waterproof covering for balconies and terraces forming a roof must be designed to fall away from any external door openings into the building. An adequate step or raised threshold must be provided to avoid the risk of wind driven rain penetrating the construction. A minimum of 75mm difference between the highest point of the balcony roof waterproof surface and the underside of the door sill may be provided as the detail below, otherwise in all other situations, a 150mm should be provided.
Drainage outlets must be easily accessible and maintainable even if decking / balcony floor finishes are applied. Balcony steelwork must be adequately protected against the potential for corrosion
Protective coatings and finishes to metals
All metals must have a suitable protective coating to minimise or prevent corrosion during its life.
For further guidance on corrosion protection and durability, please refer to Appendix C of our Technical Manual.
Roofs
For clay, concrete and slate roofing, a full roof fixing specification from the slate or tile manufacture must be provided and take into account the exposure, environment and orientation of the site.
For metal cladding, the designer must establish the environment’s corrosivity when specifying metal cladding as well as the potential for wind uplift and movement in a cladding system during severe wind conditions, particularly over party wall positions.
Warranty position
This article has provided some guidance on how the functional requirements of our technical manual can be satisfied for developments in coastal locations. For further information please refer to Appendix B of the Technical manual.
Read more articles on InSite and sign up to receive our blog round-up.
Every care was taken to ensure the information in this article was correct at the time of publication (June 2024). Guidance provided does not replace the reader’s professional judgement and any construction project should comply with the relevant Building Regulations or applicable technical standards. For the most up to date Premier Guarantee technical guidance please refer to your Risk Management Surveyor and the latest version of the Premier Guarantee Technical Manual.